Title:
|
(CD 5) Authorize Execution of Change Order No. 3 in the Amount of $77,750.00 to the Contract with Crescent Constructors, Inc., for the Village Creek Water Reclamation Facility Grit Facility and South Influent Pump Station Project for a Revised Contract Amount of $25,972,345.00, and Adopt Appropriation Ordinance to Effect a Portion of Water’s Contribution to the Fiscal Years 2022-2026 Capital Improvement Program
|