File #: M&C 25-0554    Version: 1 Name:
Type: Award of Contract Consent Status: Agenda Ready
File created: 6/4/2025 In control: CITY COUNCIL
On agenda: 6/10/2025 Final action:
Title: (CD 2 and CD 9) Authorize Execution of Change Order No. 2, in the Amount of $237,052.00 and the Addition of 25 Calendar Days to the Construction Agreement with William J. Schultz, Inc. dba Circle C Construction Company, for the Installation and Maintenance of a Temporary Pedestrian Trail for a Revised Contract Total in the Amount of $9,504,922.00, Adopt Appropriation Ordinance, and Amend Fiscal Years 2025-2029 Capital Improvement Program
Attachments: 1. M&C 25-0554, 2. ORD.APP_20SWM FWCC MAIN ST OUTFALL CHANGE ORDER NO. 2_52002_AO25(R2).pdf