Title:
|
(CD 2 and CD 9) Authorize Execution of Change Order No. 2, in the Amount of $237,052.00 and the Addition of 25 Calendar Days to the Construction Agreement with William J. Schultz, Inc. dba Circle C Construction Company, for the Installation and Maintenance of a Temporary Pedestrian Trail for a Revised Contract Total in the Amount of $9,504,922.00, Adopt Appropriation Ordinance, and Amend Fiscal Years 2025-2029 Capital Improvement Program
|