Title:
|
(CD 8) Authorize Execution of Change Order No. 3 in the Amount of $454,629.38 and the Addition of 20 Calendar Days to the Contract with Texas Materials Group dba Texas Bit, for Combined Street Paving Improvements, Storm Drain and Water and Sanitary Sewer Main Replacements for 2018 Water Sewer Main-J & CIP Contract 15 Project, for a Revised Contract Amount of $8,421,079.12, Adopt Attached Appropriation Ordinance to Effect a Portion of Water’s Contribution to the Fiscal Years 2022-2026 Capital Improvement Program, Adopt Attached Appropriation Ordinance and Amend the Transportation & Public Work's Fiscal Years 2022-2026 Capital Improvement Program
|