Skip to main content
File #: M&C 25-0607    Version: 1 Name:
Type: Award of Contract Consent Status: Passed
File created: 6/17/2025 In control: CITY COUNCIL
On agenda: 6/24/2025 Final action: 6/24/2025
Title: (CD 3 and CD 9) Authorize Execution of Change Order No. 3, to a Construction Contract with William J. Schultz, Inc. dba Circle C Construction Company in the Amount of $1,621,223.35 for the Westcliff Drainage Improvements, Phase 1, and Sanitary Sewer Rehabilitation Contract 91, Project Part 2, Adopt Appropriation Ordinances, and Amend Stormwater and Water Capital Improvement Program Contributions to their Respective Fiscal Years 2025-2029 Capital Improvements Programs
Attachments: 1. M&C 25-0607, 2. 20SWM WESTFLIFF CHANGE ORDER 3 Map.pdf, 3. ORD.APP_20SWM WESTCLIFF PHASE 1 AND CONTRACT 91 PT 2 CHANGE ORDER 3_56002_AO25(R2).pdf, 4. ORD.APP_20SWM WESTCLIFF PHASE 1 AND CONTRACT 91 PT 2 CHANGE ORDER 3_52007_AO25(R3).pdf