Title: (CD 2) Authorize Execution of Change Order No. 3, in the Amount of $1,498,305.57 to the Construction Agreement with William J. Schultz, Inc. dba Circle C Construction Company, for the Fort Worth Central City New Main Street Outfall Storm Drain & 8th Street Project, for a Revised Contract Amount of $11,003,227.57, Adopt Appropriation Ordinances, and Amend Fiscal Years 2026-2030 Capital Improvement Program
Attachments: 1. M&C 26-0059, 2. M&C Map_CPN103262_103666_FWCC_MainStOutfall.pdf, 3. ORD.APP_20SWM FWCC NEW MAIN ST OUTFALL CHANGE ORDER NO. 3_52008_AO26(R2).pdf, 4. ORD.APP_20SWM FWCC NEW MAIN ST OUTFALL CHANGE ORDER NO. 3_52007_AO26(R3).pdf