Title:
|
Authorize the Execution of Change Order No. 1 in the Amount of $135,060.00 and the Addition of 45 Calendar Days to a Contract with McKee Utility Contractors, Inc. for the Village Creek Drainage Basin Main 325 Parallel Relief Sewer, Part 2 Project, for a Revised Contract Cost of $13,323,507.00, Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt and Adopt Appropriation Ordinance (COUNCIL DISTRICTS 6 and 8)
|