File #: M&C 25-0971    Version: 1 Name:
Type: Award of Contract Consent Status: Agenda Ready
File created: 10/13/2025 In control: CITY COUNCIL
On agenda: 10/21/2025 Final action:
Title: (CD 8, CD 9, and CD 11) Authorize Execution of Change Order No. 2, in the Amount of $25,932.00 and the Addition of 37 Calendar Days to the Construction Contract with McClendon Construction Company, Inc. for the 2022 Bond Year 2 Contract 8 Project (West Berwick Street Quiet Zone); for a Total Revised Contract Amount of $7,403,175.00, Adopt Appropriation Ordinance, and Amend the Fiscal Years 2026-2030 Capital Improvement Program (2022 Bond Program)
Attachments: 1. M&C 25-0971, 2. M&C Map_CPN104183_WBewickSt_2022Bond_Yr2_CO2.pdf, 3. ORD.APP_202022 BOND YEAR 2 CONTRACT 8 CO2 - MCCLENDON_52002_AO26(R2).pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo