Title:
|
(CD 2) Authorize Execution of Change Order No. 3, in the Amount of $400,000.00 and the Addition of 45 Calendar Days to the Construction Contract with McClendon Construction Company, Inc. for the 2022 Bond Year 2 Contract 10 Project; for a Total Revised Contract Amount of $7,674,236.25, Adopt Appropriation Ordinance, and Amend the Fiscal Years 2025-2029 Capital Improvement Program (2022 Bond Program)
|