Title:
|
(CD 3 / Future CD 3) Authorize Execution of a Contract with Thalle Construction Company, Inc. in the Amount of $19,873,823.75 for Westside Treatment Plant III 30” Water Transmission Main Project, Authorize Execution of Amendment No. 1 in the Amount of $303,590.00 to an Engineering Agreement with Kimley-Horn Associates, Inc., for Westside Treatment Plant III 30” Water Transmission Main Project, Provide for Total Project Costs in the Amount of $21,125,743.00, Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt, and Adopt Appropriation Ordinance to Effect a Portion of Water’s Contribution to the Fiscal Years 2023-2027 Capital Improvement Program
|