Title:
|
(CD 4) Authorize Execution of a Construction Manager at Risk Contract with Steele & Freeman, Inc. with a Construction Phase Fee of 3.0%; Accept the Guaranteed Maximum Price of $9,936,177.00 for the Construction of a New Fire Station 37 within a Project Budget of $12,942,672.00, Adopt Appropriation Ordinances and Amend the Fiscal Year 2024 Adopted Budget and Fiscal Years 2024 – 2028 Capital Improvement Program (2022 Bond Program)
|