Title:
|
(CD 9) Authorize Execution of a Contract with Stabile & Winn, Inc., in the Amount of $2,026,734.45, for Combined Street Paving Improvements and Water and Sanitary Sewer Main Replacements for Round Six of the Council District 9 Street Repair and Reconstruction Program and Near Southside Medical District Water and Sanitary Sewer Main Improvements Projects, Accept Funding in the Amount of $2,000,000.00 from Tax Increment Reinvestment Zone No. 4 (Southside TIF) for the Street Repair and Reconstruction Program for a Revised Total Program Amount of $18,000,000.00, Adopt Appropriation Ordinances for Street Repair Funding and to Effect a Portion of Water Department’s Contribution to Fiscal Years 2026-2030 Capital Improvements Program, and Amend the Transportation and Public Works Fiscal Years 2026-2030 Capital Improvement Program
|