File #: M&C 24-0752    Version: 1 Name:
Type: Award of Contract Consent Status: Passed
File created: 8/21/2024 In control: CITY COUNCIL
On agenda: 8/27/2024 Final action: 8/27/2024
Title: (CD 7) Authorize Execution of Change Order No. 2 to the Construction Manager-at-Risk Contract with Byrne Construction Services, LLC, in the Amount of $830,072.86, and Authorize Additional Construction Contingency Funding in the Amount of $300,000.00, to Increase the Guaranteed Maximum Price Amount to $16,230,805.86, for the Northwest Community Center Project and the Northwest Community Center South Drive Project, and Amend the Fiscal Years 2024-2028 Capital Improvement Program  