File #: M&C 22-0800    Version: 1 Name:
Type: Award of Contract Consent Status: Passed
File created: 10/5/2022 In control: CITY COUNCIL
On agenda: 10/11/2022 Final action: 10/11/2022
Title: (CD 9) Authorize Execution of Amendment No.1 to City Secretary Contract No. 57409, a Construction Manager at Risk Agreement with Dean Electric, Inc., dba Dean Construction, in the Amount of $1,009,464.00 for the Fire Station Park Expansion Project, for a Revised Contract Amount of $2,512,964.00; Accept Funds in the Amount of $650,000.00 from Tax Increment Reinvestment Zone #4 - Southside Medical District; Adopt Appropriation Ordinances and Amend the Fiscal Years 2022-2026 Capital Improvement Program
Attachments: 1. M&C 22-0800, 2. LOCATION MAP.pdf, 3. ORD.APP80FIRE STATION PARK CMAR AGREEMENT AMENDMENT NO.1_30286_AO22(r2).pdf, 4. ORD.APP80FIRE STATION PARK CMAR AGREEMENT AMENDMENT NO.1_30110_AO22(r3).pdf